Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Planning Approval topic
No spam. Unsubscribe anytime.
Robeson supervisors grant waiver and conditionally approve Book Site School plan
Summary
The board conditionally approved the Book Site School plan with standard technical conditions and separately granted a waiver from §403 allowing a combined preliminary/final submission, subject to remaining engineer review items and escrows.
Get email alerts on the Planning Approval topic
No spam. Unsubscribe anytime.
Robeson Township supervisors voted to approve a preliminary/final plan for a proposed Book Site School on Zion Road, granting a waiver from section 403 to allow the developer to submit the plan as a combined preliminary and final application.
The township engineer presented a review letter dated 07/06/2026 outlining outstanding items, including standard escrows, a developer’s agreement and post-construction stormwater-management conditions. The board approved the plan subject to those remaining technical conditions and the engineer’s final sign-off.
Board members also separately moved to grant the §403 waiver that permits the combined preliminary/final review; the waiver passed unanimously among members who voted on that motion.
What happens next: The engineer’s outstanding technical items and required agreements remain to be completed and the project team was told it does not need to return to the board next week for a vote on the same submission, provided the conditions are met.
Why it matters: The waiver and conditional approval allow the school project to advance through design and permit coordination while the developer completes bonding, escrows and post-construction stormwater obligations.