Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Madison County accepts final payments and closeout materials for Seyler Lane Bridge project
Summary
The Madison County Commissioners approved Application for Payment No. 2 ($680,392.14), Draw Request No. 10 (final, $233,972.89), and the project completion report for the MT-MCEP-CG-25-050 Seyler Lane Bridge on June 30.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Madison County Commissioners on June 30 approved final payment and closeout items for the Seyler Lane Bridge (project code MT-MCEP-CG-25-050).
Commissioner William A. Todd moved to approve Application for Payment No. 2 in the amount of $680,392.14 for the Seyler Lane Bridge project; Commissioners Duke W. Gilman and Ron E. Nye voted in favor. The board also approved Draw Request No. 10, listed as the final draw, in the amount of $233,972.89, and accepted the Project Completion Report. Commissioners approved an Acknowledgment of Responsibility letter and a Certification of Guarantee as part of the closeout documentation.
Grants Manager Shawna Lutgen was recorded as the county commentor for these items. The meeting minutes indicate the motions passed unanimously; no dissenting votes or conditions were recorded. The minutes do not provide contractor payment breakdowns beyond the listed amounts or state whether any retainage remains beyond the final draw request.