Seaside Park moves forward with stormwater-pump-station procurement items for regular meeting

Mayor and Council of Seaside Park · March 20, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council discussed two Remington Burnick Engineers proposals covering construction-management inspection and procurement support for 14th Avenue stormwater pump station; staff said bid specs exist but construction bids have not been issued and components will be split for rebid.

Seaside Park officials reviewed two proposals dated March 11, 2026 from Remington Burnick Engineers related to the 14th Avenue stormwater pump station during the March 19 work session. The first proposal covers construction management and inspection (listed for consideration as resolution 226157) and the second provides additional procurement work for stormwater-management equipment (resolution 226158) to be considered later at the regular meeting.

Staff told the council that design, permitting and bid specifications have been paid for but the actual construction bid package has not yet been issued; the project will be rebid with the equipment and generator components separated into individual bid packages. The council indicated these items would move to the regular meeting for action.

Residents asked whether the construction bid package had been released; staff said they would follow up with a timeline. No contract awards or final votes occurred during the work session.