Council approves $158,733.77 change order to add ADA sidewalk on North Street storm-sewer project

Hannibal City Council · April 22, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The council approved a $158,733.77 change order for phase 2 of the North Street storm sewer project to add an ADA-compliant sidewalk and required traffic control; the project is funded in part by a $5 million ARPA award and phase 2 construction is budgeted at $2.53 million.

The Hannibal City Council on April 21 approved a $158,733.77 change order for phase 2 of the North Street storm sewer project to install an Americans with Disabilities Act–compliant sidewalk and additional traffic-control measures required by the Missouri Department of Transportation permit.

Darren Gordon, general manager of the Board of Public Works, told the council the city was awarded $5,000,000 in ARPA funds to rebuild the failed North Street storm sewer. He said phase 1 of the project cost $1,773,000.08 and that approved phase 2 costs are $392,000 for engineering and $2,533,639.74 for construction. "After review of the requirements and available funding, it is recommended to move forward with the approval of change order number 1 of the North Street storm sewer phase 2 project," Gordon said.

Council members asked questions about ADA compliance and project timing. Gordon said some existing sidewalks in the project area do not meet ADA slope and detectable-warning requirements and that the contractor submitted $158,733.77 to complete the ADA-compliant sidewalk and additional traffic-control items necessary to meet MoDOT's permit conditions. He said phase 1 came in under budget, leaving approximately $301,360.18 available; the proposed change order fits within the remaining phase 2 allocation.

The council approved resolution 26-05-26 authorizing the mayor to execute the $158,733.77 change order. Roll-call responses recorded the measure as carried.

What happens next: With council approval, the contractor may proceed with the additional sidewalk work and traffic-control installations under the change order; the council did not set a separate implementation deadline at the meeting.

Sources: remarks of Darren Gordon and resolution readings at the April 21, 2026 council meeting.