Highway director reports flood damage, federal bridge project on track with major PE award

Orange County Board of Commissioners · July 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Orange County highway director reported June 27 flooding that caused washouts and closures, and updated commissioners on Federal Bridge 28: right-of-way engineering is 50% complete, environmental work has started, the PE agreement totals $204,300 (county share $20,430) and a larger $918,000 award is tied to the project; the bridge is scheduled for landing Oct. 11, 2029.

Carl, the highway director (speaker 7), told the commission crews responded to another countywide flood on June 27 that left multiple roads underwater and caused washouts to culverts and bridges. "The guys had worked feverishly to try to get those all corrected," Carl said, and he thanked staff who installed high-water signs and barricades.

Carl gave a substantive program update on Federal Bridge 28. He said the right-of-way engineering is about 50% complete and the environmental documents work has started. He reported a preliminary engineering (PE) agreement worth $204,300; the county's share would be roughly $20,430 under a 90% reimbursement arrangement. Carl also said the total award on the contract was $918,000 for the broader federal project and noted that Bridge 28 is scheduled to begin construction landing on Oct. 11, 2029.

Chair (speaker 3) and other commissioners asked clarification questions about fleet and equipment purchases tied to highway operations. The highway director said district crews continue ditching and other post-flood repairs.

Commissioners did not take additional binding action on the bridge timetable at the meeting; staff said design and environmental steps were still under way and that right-of-way acquisition work is ongoing.