Algoma staff report progress on fire/rescue building, admin/police facility and Fremont Street environmental review
Summary
City staff reported that steel for the new fire/rescue building was delivered and work will begin on footings this week; plans for administration and police facilities have markups and will be reviewed by consultants; environmental review for the Fremont Street library starts Thursday and TID 5 utility bids are due on the 10th.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
City staff provided construction and project updates at the Algoma Common Council meeting Dec. 1, reporting progress on the new fire and rescue building, the administration and police building plans, and an environmental review at the Fremont Street library.
Matt, a city staff member, told the council the steel structure for the fire and rescue building has been delivered and crews will begin digging footings; he said a block wall where the lower and higher building sections meet will be built next, and some higher-cost equipment items (for example, a compressor) are being ordered now although delivery and warranty timelines extend into the summer of 2026. "Once that wall is built, you'll see in a pretty quick courteous structure start to go up," Matt said.
Staff also reported they received marked-up plans for the administration and police department project and will meet with Bayland and MEP consultants; staff expect a final plan set to present to council after those reviews and a clearer timeline once bids are returned.
Environmental consultants will begin work at the Fremont Street library on Thursday morning to complete environmental checks; the firm will then move from the library to City Hall so staff can assess the City Hall building options. Separately, bids for utilities tied to the TID 5 developer project (water, sanitary sewer, storm sewer, electric, gas) are due on the 10th and will be reviewed by finance and personnel before council consideration.
Councilors asked about start dates, and staff estimated utility work would likely start in April; land acquisition and contract execution were described as prerequisites to beginning physical work.
The council received the updates with no votes required; next steps are for staff to finalize bid review schedules and bring procurement items back to council for action.