Selectmen accept zoning and health-officer report; DES says culvert work likely required wetland notification

Board of Selectmen · January 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Board accepted the zoning/health officer report, approved multiple permits (stand-by generators and a temporary mobile home), and heard that DES finds a culvert project on Pettengill Road likely requires a wetland permit/notification and further NRCS review.

The Board of Selectmen accepted the Zoning Coordinator/Health Officer report on Jan. 12 and ratified several permits, including stand-by generator permits for James Dewkett and Tim Moultor and a temporary mobile home permit for Jody Barry following a residence fire.

Tim Bray reviewed vested and non-vested permit statuses and reported he sent updated site-plan review packets to applicants on Jan. 1. Bray also summarized correspondence about a culvert and access-road installation on Pettengill Road: Emmanuel Uwizeye of the NHDES Wetlands Bureau reviewed site details and concluded a wetland permit (notification) is required, noting the area could be a Priority Resource Area, swales may meet wetland criteria, and the site may lie in a floodplain; NRCS was noted as likely to investigate further.

Selectman Steve Dzubak moved to accept the Zoning Coordinator/Health Officer report as written; Jen Roberts seconded and both voted in favor. Bray also reported approval of an ISDS construction permit for a three-bedroom residence (Casey and Elizabeth Brennan).