NHDES says culvert work on Pettengill Road likely requires wetland permit; town to monitor

Board of Selectmen · February 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

After a resident reported installing a culvert on Pettengill Road and suggested no permit was needed, a Wetlands Permitting Specialist at NHDES replied that a wetland permit/notification is required and noted potential Priority Resource Area and floodplain impacts; the board will monitor permitting progress and NRCS review.

James Yaegar met with the board to discuss culvert placement and access work on Pettengill Road and said he believed no permit was required. The Wetlands Permitting Specialist in the NHDES Land Resources Management Water Division reviewed materials and responded that a wetland permit or notification is required, citing Env‑Wt 901.03 (exemptions) and guidance in Part Env‑Wt 308. The specialist said the site appears to be in a Priority Resource Area and may involve wetland features that require verification by a certified wetland scientist; floodplain location increases the likelihood of permit requirements.

The NHDES response also noted that the Natural Resources Conservation Service (NRCS) may investigate the site further. The Select Board said it will monitor NHDES permitting progress and related NRCS actions. The board did not take a formal enforcement vote at the Feb. 9 meeting; the NHDES guidance in the record frames the next steps for permitting and technical review.

The record to date is administrative: NHDES advised that a permit/notification is required and identified the statutory and regulatory sections to consult. Any required permit, wetlands determination, or enforcement action would follow the agency’s procedures and any subsequent technical findings from NRCS or a certified wetland scientist.