Thayne council approves $383,207 street pay request, advances sewer study and equipment purchase

Thayne Town Council · October 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Thayne Town Council on Oct.16 approved pay request #1 for the 2024 Street Improvement Project including change orders totaling $383,207.35, authorized a sewer-line study aimed at SLIB funding, and approved buying an aftermarket sweeper head assembly for $5,830.24.

The Thayne Town Council voted Oct. 16 to approve a major pay request tied to the town's 2024 Street Improvement Project and authorized several operational moves tied to street and sewer infrastructure.

Council approved pay request #1 to Avail Valley Construction, including change orders totaling $383,207.35, after a presentation from Kade Smith of Sunrise Engineering explaining recent repairs and the plan to schedule a final walkthrough. The council's motion to approve the pay request was moved by Councilmember Heward and seconded by Councilmember Woolley; the motion carried.

Sunrise Engineering also briefed the council on the North Sewer Line and potential expansion. Smith said the engineering team, Mayor Devin Simpson, a town staff member identified as Cliff and Councilmember Woolley discussed alternatives to adding lagoons, including a smaller mechanical treatment plant footprint. The team intends to pursue a State Loan and Investment Board (SLIB) application at SLIB's next meeting in February to secure funding for the study and possible expansion.

The council addressed municipal equipment needs during the streets report. Councilmember Woolley said the street sweeper requires a new head assembly. The manufacturer quoted $8,592.48 plus $400 shipping, while an aftermarket option was available for $5,830.24 (shipping included). The council approved purchasing the aftermarket assembly (mover: Councilmember Woolley; second: Councilmember Pelletier); the motion carried.

Votes at a glance: pay request to Avail Valley Construction for the 2024 Street Improvement Projects (change orders total $383,207.35) ' approved (mover: Heward; second: Woolley). Purchase of aftermarket sweeper head assembly for $5,830.24 ' approved (mover: Woolley; second: Pelletier). Several routine finance motions (issuing checks to be ratified, payment of bills) were also carried.

Why it matters: The pay request advances a multi-hundred-thousand-dollar capital project that affects local streets and utilities. The sewer-line study could change long-term wastewater infrastructure needs and land use (mechanical plant footprint versus additional lagoons), and equipment procurement affects winter maintenance capacity.

Next steps: Sunrise Engineering and town staff plan a final walkthrough for the street project and will continue work on documentation for a SLIB submission in February. The aftermarket sweeper part will be acquired and installed ahead of winter preparations.

Sources: Town meeting minutes and agenda items presented Oct. 16 by Sunrise Engineering and town staff.