Council declines surplus appropriation for Diamond Park restroom and concessions after heated debate

Plaquemines Parish Council · July 10, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A $172,009.68 appropriation from surplus to complete Diamond Park restroom and concession work failed to meet the supermajority requirement; the motion received a 5–4 majority but did not reach the six votes required for surplus-funded appropriations.

Plaquemines Parish Council debated and then rejected a surplus-funded appropriation on July 9 to complete Diamond Park restroom and concession work after a lengthy exchange over project scope and cost.

Council member LaFrance offered the appropriation of $172,009.68 to bring the project to a $550,000 total, saying the funds would finish construction; the administration reported the project budget stood at $377,990.32 to date. Supporters argued the restroom and concession facility — which includes a concession stand and storage area in addition to bathrooms — would serve children and recreational users in the southern end of the parish.

Opponents said bids came back well over the parish’s available funds, questioned construction methods and resilience-driven building requirements, and urged rebidding or design modifications to fit the parish’s budget. Council member Champagne called the proposed building an overbuilt structure and pushed for a smaller, less expensive option; others recommended soliciting alternative bids or design changes to bring the price down into the current funding envelope.

The vote to appropriate surplus funds passed on the council floor by a 5–4 roll call, but the motion required a six-vote supermajority because the funding source was surplus. The chair announced the measure failed for lack of the required supermajority.

What’s next: Council members asked engineering and administration to explore alternatives: rebidding with revised scope, soliciting alternative contractors, or identifying tradeoffs (for example, scaling back storage or the roof system) that could bring the project within the available budget.