Summary

The North Little Rock School District Board approved bids to replace failing walk‑in coolers and freezers at Boone Park and Lakewood after staff reported compressor failures that sent metal fragments through units; staff said replacements are in the child nutrition budget and outlined a maintenance rotation to limit future failures.

The North Little Rock School District Board of Education voted to accept bids to replace walk‑in coolers and freezers at Boone Park and Lakewood after district staff described a catastrophic compressor failure that damaged internal components.

A district staff member told the board the failure “sent metal and it sent fragments through” the system and recommended full replacement rather than piecemeal repairs, saying partial fixes risk damaging a new compressor. “The inside parts, that's what's failed,” the staff member said.

The issue prompted questions about timing, cost and warranties. The staff member estimated retrofit replacement for a walk‑in cooler or freezer could be “upwards of 60 to 100,000” dollars because some installations may require crane work or nonstandard panels. He said typical installation warranties the district has received are usually one year for parts and labor.

Staff also outlined a preventative‑maintenance plan. To allow technicians to clean coils and service evaporators, the district plans a rotation that takes some units offline during school breaks and summers so boxes can be warmed and serviced. The staff member said the district hopes to move to a rotation of roughly every two to three years and noted current warehouse capacity limits how much food can be shifted if another unit fails.

Board members confirmed the expense will come from the child nutrition budget. “This is all part of your budget — not out of the operating budget,” one board member said, noting funds are available.

A motion to accept the bids for Boone Park and Lakewood was made and seconded and the board approved the procurement by voice vote. Following the vote, a board member said staff should “Start next week.”

The approved replacements are intended to restore capacity for the district's meal program and to reduce the risk of repeated breakdowns; staff said work could take place over multiple summers to avoid disrupting food service operations.