Millsboro moves inspections to KCI, reduces Century Engineering services for force‑main work
Summary
After citing challenges with Century Engineering on the force‑main project, council voted to reduce Century's construction‑inspection role and move oversight to KCI to avoid conflicts and improve project oversight.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Council voted July 6 to reduce the scope of services provided by Century Engineering for the beneficial reuse and force‑main contracts and to transfer inspection oversight to KCI.
Staff told council that Century had been the original design firm for parts of the pipeline work but that performance issues and coordination problems had jeopardized USDA funding and required closer day‑to‑day oversight. A staff member said KCI had already identified change‑order issues and was prepared to provide inspection and construction administration. "We're trying to put everything under their umbrella," a staff member said, describing KCI as the more reliable partner for the work.
Council members asked whether shifting work to KCI would require redundant reviews or extra cost; staff said minimal duplication was possible but that KCI would pick up ongoing inspection and oversight and that the town would reduce Century's role to the smallest practical scope. The motion to reduce Century Engineering's services for the force‑main/beneficial reuse project passed by voice vote.
Council asked staff to capture any costs that are repeat efforts and to report back on savings or duplicative charges.