Oakland hears community energy plan presentation; public comment open through May 27
Summary
A consultant presented a draft community energy plan funded by a $10,000 grant; the plan lists initiatives such as municipal solar, EV charging and outreach for low/moderate‑income households and aims for council adoption by mid‑July to close out the grant.
Get email alerts on the Energy topic
No spam. Unsubscribe anytime.
Oakland council members on May 12 received a presentation from planners working on a community energy plan funded by a $10,000 state grant and opened a public comment period that closes May 27.
Dan Halvin (speaker 8), a planner with T and M Associates, said the plan is intended as a town‑level roadmap to understand local energy use, set priorities aligned with the New Jersey Energy Master Plan and help the borough compete for implementation grants. "It’s a town level road map that helps municipality understand its energy use, set local priorities that align with the New Jersey Energy Master Plan to create a cleaner, more resilient, and affordable energy future," Halvin said.
Halvin presented data showing overall municipal energy use has declined in recent years, noted growth in electric vehicles between 2015 and 2020 and said state data currently show no public EV charging stations inside borough boundaries. The plan’s draft menu of initiatives includes installing renewable generation on municipal buildings, adding EV charging infrastructure, electrifying the municipal fleet and targeted outreach and assistance for low‑ and moderate‑income households to access efficiency programs.
Council members asked about eligibility for EV charging grants and whether the borough’s income level would disqualify it from some programs. Halvin said several state programs are available and the borough should qualify for general funding; some programs are targeted at non‑affluent communities but other general grants exist. Members of the public raised concerns about using tax dollars for charging stations; resident William Sysdig (speaker 14) urged the borough not to use municipal tax money for EV stations and suggested private businesses could host charging points.
Halvin said the grant requires adoption of a community energy plan by July 15 to allow the borough to close out the grant by July 31, and staff are targeting an internal draft in late June for a public adoption vote in late June or early July. The presenter provided an email address for comments and asked residents to submit input by May 27 to be considered for the final document.
No binding commitments of local funds were made at the meeting; council members discussed program eligibility and possible locations for chargers but deferred implementation details to staff and future agenda items.