Franklin County reports progress on courthouse remodel; new court staff introduced
Summary
Commissioners reviewed progress on the courthouse addition and other county buildings, including an April 8 court move timeline and bids for Search and Rescue facilities, and introduced new trial court administrators who raised concerns about Idaho Supreme Court IT support.
Get email alerts on the Courthouse Remodel topic
No spam. Unsubscribe anytime.
Franklin County Commissioners on March 25 reviewed building updates for the courthouse and other county facilities and welcomed new trial court administrators.
Randy Henrie, listed in the record as Building Maintenance and Planning and Zoning, told the commissioners the Clerk’s Office is moving supplies and will complete its final move the next day and that the court office relocation is on schedule for Monday, April 8. Henrie said the Assessor building is finished and ready for staff to move in once desks arrive. He added that the Search and Rescue building’s engineering work is complete and the county is accepting bids for cement, HVAC and electrical work. Two new drinking fountains have been installed in the Robinson Building, and Henrie plans to construct a chute on the north side of the courthouse to begin remodeling the court floor.
The introductions of Jason Dye (Trial Court Administrator), Lacy Parker (Deputy Trial Court Administrator) and Davey Burnell (Family Court Manager) followed the building update. Commissioners expressed frustration with the level of support from the Idaho Supreme Court IT Team for the new courtroom and asked for more involvement to assist with the remodel of the old courtroom.
Why this matters: The schedule and infrastructure decisions affect when court operations can move into updated spaces and how services to residents will be delivered while remodeling is under way. The Search and Rescue building and courtroom changes require contracting and oversight that could affect timelines and budgets.
The commissioners did not take final votes on construction contracts during the meeting. The board set its next meeting for Monday, April 8, 2024.