Public Works approves stormwater agreements and awards $108,572 contract for Skyline Drive storm‑sewer replacement
Summary
The Board of Public Works approved two stormwater maintenance agreements — for a multifamily development and for Green Tree Elementary — and awarded a rebid contract for the Skyline Drive storm‑sewer replacement to BMCI Construction at $108,572 (contingency to $116,000) after staff described design changes that reduced excavation and overall cost.
Get email alerts on the Stormwater Infrastructure topic
No spam. Unsubscribe anytime.
The Board of Public Works on July 6 approved routine stormwater maintenance agreements tied to development permits and awarded a rebid contract for a failed storm sewer on Skyline Drive, with staff citing redesigns and rebidding savings.
Agreements explained: Public‑works staff (Max) presented a standard stormwater maintenance agreement accompanying the city’s stormwater management permits for a multifamily development at the southwest corner of East Paradise Drive and South River Road (SWMPW26‑03) and a separate agreement for redevelopment at Green Tree Elementary School (SWMPW26‑05). The Green Tree project includes a new asphalt parking lot, detached garage, drive lanes, concrete walkways and on‑site stormwater practices including a bioretention basin. For the multifamily agreement, staff said final contract language remained under review by the city attorney and the developer’s counsel and asked the board to approve contingent upon the city attorney’s final sign‑off.
Skyline Drive contract award: Staff reviewed last month’s rejected bid — nearly double the earlier estimate — and described changes in the redesign that reduced excavation depth and clarified special provisions. City staff said rebidding produced a low bid of $108,572 from BMCI Construction and recommended awarding the work to BMCI with approximately 7% contingency for a total allocation not to exceed $116,000. Board members asked whether the redesign or changes in engineering reduced the cost; staff said shallower excavation and clarifications in the special provisions reduced quantities and lowered cost for items such as unclassified excavation and street work.
Motion and outcome: The board approved the stormwater maintenance agreements (one approval contingent on city‑attorney sign‑off) and awarded contract 26‑10 to BMCI Construction by voice vote.
Impacts and schedule: Staff said the Skyline Drive sewer replacement addresses a failed storm sewer that created a sinkhole on private property; BMCI is a known local contractor and the city expects work to proceed this summer. The Green Tree work will improve on‑site stormwater management for the school redevelopment. The multifamily agreement will be brought back with final signatures for mayor and clerk once attorney language is resolved.
Quotations: “We were able to lower one section of pipe so it’s much shallower,” Max said, describing a redesign that reduced excavation and cost.
Next steps: Staff will return the finalized agreements to the mayor and clerk for execution once legal language is settled; the Skyline Drive construction will proceed after contract execution.