Commissioners weigh repairs after culvert collapse on 1,000 West; Community Crossings work targeted for mid‑August
Summary
County highway staff reported a collapsed 48‑inch culvert on 1,000 West near Dairy Road and recommended temporary rock placement, locates and replacement; Community Crossings construction is expected to start in mid‑August and a new dump truck is on order though upfitter work may not complete until October.
Get email alerts on the Roads Infrastructure topic
No spam. Unsubscribe anytime.
Highway staff updated the Warren County commissioners on storm damage and a collapsed culvert on 1,000 West (Dairy Road), describing immediate and near‑term repair plans and scheduling for a larger Community Crossings project.
S1 told the board the culvert “collapsed…that 48 inch across the road,” and said crews would “put more rock on it” as a temporary measure and obtain locates for a permanent replacement. Commissioners discussed pipe diameter options — including whether to use a 36‑inch versus a 48‑inch pipe — and agreed staff would consult Randy about appropriate sizing.
S1 also reported that State Road 55 repairs were completed and that the Community Crossings contract with the selected contractor is targeting mid‑August to begin work on county projects. The county’s new dump truck has arrived from the dealer but the upfitter may not finish outfitting the truck until October, meaning the vehicle will be paid for when completed.
Why this matters: the collapsed culvert affects a local collector road and requires both temporary traffic/grade control and a permanent replacement; timing affects local access and future budgets for materials and construction.
Next steps: highway staff will place temporary stone where needed, obtain locates and proceed with replacement work once materials and sizing are confirmed; the county expects to advertise/award related contracts at the next budget meeting and begin Community Crossings work in mid‑August.