Committee recommends village board approve two-night overnight paving at roundabout
Summary
Contractors requested permission for two consecutive nights of overnight milling and paving at the County Highway N and TT roundabout to avoid daytime queuing and improve final pavement quality; the committee recommended the village board approve the overnight work.
Get email alerts on the Road Construction topic
No spam. Unsubscribe anytime.
Contractor representatives asked the committee to recommend village board approval for two consecutive nights of overnight work to mill and finish-pave the roundabout at County Highway N and TT.
A contractor explained that daytime repairs have caused considerable queuing and safety concerns since County Highway N is acting as a detour route, and that completing milling and paving in one overnight operation produces a "better product" than patching over multiple daytime shifts. The contractors reported they have coordinated with emergency responders and that WisDOT has already permitted some minimal overnight ramp work. The contractors indicated the work is proposed for mid-August and that neighborhood outreach would follow once plans are finalized.
After questions about timing, outreach to nearby employers and residents, and whether the delivered overnight unit would be the one ultimately owned, a committee member moved and another seconded to recommend the overnight hours request to the village board. The motion passed by voice vote; the transcript does not record a roll-call tally.
The village board will receive the committee’s recommendation; any overnight permit will be subject to final conditions set by the board and the village’s noise and construction policies.