Elkton council approves 34‑home Floral Springs subdivision after 3–3 split; mayor breaks tie
Summary
The Elkton Town Council approved MSK, LLC’s Floral Springs subdivision — 34 single‑family homes on Florist Road — after a 3–3 roll call that Mayor Joshua J. Gooden broke with a deciding vote. Council debate centered on traffic, water capacity and whether phasing or open space could be required.
Get email alerts on the Land Use topic
No spam. Unsubscribe anytime.
The Elkton Town Council on Nov. 17 approved MSK, LLC’s Floral Springs subdivision, a by‑right plan to create 34 single‑family homes on Florist Road, after a 3–3 roll call that Mayor Joshua J. Gooden broke with a deciding vote in favor.
The vote followed a staff presentation and Council discussion of infrastructure and code compliance. Community Development Director Delores Hammer told Council the Elkton Planning Commission unanimously recommended approval and that the proposed lots comply with Town Code R‑3. Jonathan Garber, principal engineer and co‑owner of Lineage Architects, said the developer will extend water and sewer lines to the Town main, add required hydrants and install an 8‑inch main that he said would improve flow and pressure. Garber also said VDOT’s September 2025 traffic data showed little impact at the Florist Road/Old Route 33 intersection.
Vice‑Mayor Rick Workman moved to accept the Planning Commission recommendation; Council member Rachel Michael seconded. The roll call was recorded as yes: Louis Heidel, Rachel Michael and Rick Workman; no: Aaron Napotnik, Virginia Fulginiti and Jan Hensley. Mayor Joshua J. Gooden cast the tie‑breaking yea. The motion carried.
Town Attorney Quinton Callahan advised that the subdivision review is ministerial if the application meets the Town’s code and that denial would require a specific legal basis. “The law was pretty clear that when it came to the subdivision application, it was purely a ministerial act,” Callahan said during the discussion.
Council members raised several concerns during debate. Council Member Virginia Fulginiti and Council Member Jan Hensley asked about traffic impacts and whether phasing could be imposed; Garber said the plan contains no phasing and that phasing was not part of the submitted application. Hensley also asked whether there would be any cost to the Town for extending water and sewer; Public Works Director Gaither Hurt said the developer is responsible for bringing lines to the Town’s pipe. Council Member Louis Heidel noted the developer’s site layout prioritizes housing lots and does not include dedicated open‑space reservations or recreational facilities.
The staff summary and submitted plans specify developer responsibilities and design features: a 10‑foot easement to bring Florist Road and interior roads to a 50‑foot right‑of‑way; 7.5‑foot side setbacks to allow for utility easements; a 5‑foot sidewalk with a 4.5‑foot grass buffer; 100‑foot cul‑sacs to meet fire‑truck turning requirements; and a lighting plan conforming to Dominion Energy requirements. Rockingham County was identified as the reviewer for storm‑water runoff provisions shown on sheet C‑04D.
Public commenters had urged caution before the vote. Ronnie Merica II and other residents expressed concern about added traffic, potential infrastructure strain and preserving the town’s character; one resident had previously said a different figure for the number of homes in circulation, an inconsistency noted during the meeting.
The Council approved the subdivision by roll call and the required ministerial finding that the application met the Town’s code. The project schedule in the record indicates the developer hopes to break ground in spring 2026; no phasing condition was added. The Council did not add code changes or conditions beyond those required by existing regulations; Council members discussed broader code revisions separately.