Borough seeks $1.38 million DCED multimodal grant to rebuild Adams and Veil Street and add sidewalks

Finance Committee · July 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

A borough presenter described a complete rebuild of Adams and Veil Street—excavating over a foot and installing four pavement layers—after cores showed inadequate structure and a recent sinkhole; total estimated cost is $1.5 million and the borough will request $1,376,686 from the Pennsylvania DCED multimodal fund with a 10% local match.

The finance committee reviewed a proposed multimodal transportation grant application to rebuild Adams and Veil Street.

Will, the presenter, said cores from Remington and Bernick showed the existing pavement lacked the four-layer structure required for long-term durability and that a recent sinkhole highlighted the need for a full rebuild. The proposed project would excavate more than a foot and install four layers — subbase, base course, binder course and wearing course — and would add sidewalks to close two gaps (one between the daycare and Adams Street and another where future Wyeth site work will link sidewalks).

Estimated total project cost is $1.5 million; the borough will apply to the Pennsylvania Department of Community and Economic Development Multimodal Transportation Fund for $1,376,686. Will said typical grant practice requires a municipal resolution and noted grant applications are more competitive with a local match; he proposed a 10% match (approximately $137,000).

Public commenters asked whether restricting truck access would change the need for the project; council members and speakers observed the road has long been neglected, with severe ruts and a recent sinkhole that make rebuilding necessary.

Ending: Staff seeks a council resolution to accompany the DCED grant application due July 31; the match amount and funding source were discussed and staff will finalize the application and return with any required formal vote or resolution.