Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Capital Projects topic

No spam. Unsubscribe anytime.

Town receives construction update: Station 25 and Public Utilities Building on track for 2026

Surf City Town Council · November 22, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Contractor update: Station 25 is moving to vertical construction after a Nov. 25 delivery of a pre‑insulated metal building; staff expects Station 25 finished by May–June 2026 and the Public Utilities Building by July 2026, with mixed budget variances reported.

Nate Stroven updated the council on Station 25 and the Public Utilities Building, describing recent site work and near‑term construction milestones.

Stroven said trailers have been positioned and equipment will be delivered Monday to begin grading and concrete work; a pre‑insulated metal building is due Nov. 25, after which the contractor will "start going vertical" and aims for a May–June 2026 completion for Station 25. For the Public Utilities Building, demolition and underground plumbing/electrical are complete; a slab pour was scheduled for next Tuesday and vertical framing was expected to start Dec. 1, with a target completion of July 2026.

A budget update reported Station 25 roughly 3% under buyout and the public utilities portion about a quarter‑million dollars under budget on items that have been purchased; storage/maintenance building pricing and design work will be presented to council in January. Council thanked the contractor for site maintenance during demolition and requested continued schedule updates.