Findlay supervisors confront doubled garage quote for Recreation & Sports Complex, consider pole‑barn alternative

Findlay Township Board of Supervisors · June 25, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Manager Tom Garrett told the board a three‑bay garage quote rose from $74,900 in October to $155,000 because of material cost increases; the project budget is $99,500 and Supervisor Raymond Chappell suggested a pole‑barn alternative estimated at about $48,000 with Public Works pouring the floor.

Manager Tom Garrett reported the October quote for a three‑bay garage at the Recreation & Sports Complex was $74,900 but the current quote is $155,000 "due to increases in materials," while the board had budgeted $99,500 for the project. Supervisor Raymond Chappell suggested a pole barn alternative that Mr. Garrett estimated would cost in the $48,000 range with Public Works pouring the flooring.

The board requested Mr. Garrett to continue reviewing options but emphasized maintaining quality. No procurement decision was made at the workshop; the quotes and options will require follow up before the board moves forward.