Board approves stormwater inventory task order, moves 38th Place and County Line culvert projects to bid

Hoover Sanitary Stormwater District · March 24, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The board approved a stormwater-inventory task order (2026‑01), authorized plans and bidding for 38th Place phases 1–2 (estimated $5.3M with contingency), and reissued bid documents for the County Line culvert project to run concurrently.

The Hoover Sanitary Stormwater District approved a task order to continue its stormwater inventory and mapping work and authorized bids for two major capital projects: the 38th Place (Fillmore) improvement project and the County Line culvert replacement.

Staff presented task order 2026‑01 for the stormwater inventory and said packet figures had been updated; the earlier packet number of $229,000 was discussed in the meeting and staff noted the budget was being managed to keep the overall program amount similar to the prior year (not to exceed $300,000 as discussed). The board approved the task order to proceed with inventory, mapping, and assessment work.

On the 38th Place project, staff said phases 1 and 2 are ready to bid and estimated combined costs of about $5.3 million, including a 15% contingency. Staff outlined a schedule with a pre‑bid conference and a May 7 bid opening to allow award at the May 12 meeting. The board voted to issue plans and advertise for bids for phases 1 and 2. Members also approved reissuing bid documents for the County Line culvert project to run concurrently (with a shorter bid window and award anticipated earlier in April).

Board members stressed coordination with adjacent jurisdictions and mapping of infrastructure that crosses railroad and county lines; staff said the inventory work and upcoming bids aim to clarify ownership and maintenance responsibilities before construction.