Fayette County approves $1.22 million revision for sheriff’s watch office renovation, transfers $80,269 in SPLOST funds
Summary
The Board approved Change Order #2 for the Sheriff’s Watch Office Renovation (Contract #2436-B) adding card access readers and CCTV, transferring $80,269.06 between SPLOST accounts and revising the contract total to $1,220,327.04.
Get email alerts on the Procurement topic
No spam. Unsubscribe anytime.
Fayette County’s Board of Commissioners voted 3-0 on July 10 to approve Change Order #2 for the Sheriff’s Watch Office Renovation (Contract #2436-B) to HEC Construction Solutions, LLC, adding card access readers and CCTV to the project and transferring $80,269.06 from SPLOST P23AH to P23AG.
Tim Symonds, consultant for the project, told the board the renovation encountered several issues that needed addressing to ensure safety and functionality of the relocated watch office and noted additional exterior improvements including re-decorations and signage. Symonds presented the requested transfer and revised contract total of $1,220,327.04.
Vice Chairman Edward Gibbons moved to approve the change order and SPLOST transfer; Commissioner Charles W. Oddo seconded. The motion passed 3-0. Commissioners Eric K. Maxwell and Charles D. Rousseau were absent.
The item authorizes staff to process the SPLOST fund transfer and execute the change order with HEC Construction Solutions, LLC. Follow-up tasks assigned include processing the financial transfer and finalizing the contract modification; the county listed an implementation target date for administrative processing.