Emmons County awards Cattail Bay Road stabilization contract to Williams Excavation
Summary
The Emmons County Commission voted to award the Cattail Bay Road cement-stabilization and graveling contract to Williams Excavation after receiving two bids; Williams’ low bid was roughly $740,454, below the engineer’s $775,000 estimate. Commissioners discussed timing, harvest traffic and gravel specifications before approving the award and authorizing signatures.
Get email alerts on the Road Construction topic
No spam. Unsubscribe anytime.
Emmons County commissioners voted to award the Cattail Bay Road cement-stabilization and graveling contract to Williams Excavation after road staff reported two bids and recommended the lower bid.
Road Department staff told the commission they received two bids: “Knife River Materials, their bid was approximately $1,040,000,” and “Williams excavation, their bid was $740,000 approximately,” and noted the engineer’s estimate was $775,000 (Presenter - Road Department (Speaker 6)). Staff said Williams has experience with similar work and could start in mid-September, with a completion window around Oct. 16.
Commissioners raised concerns about timing during harvest and local traffic. One commissioner said crews and harvest activity would make coordination important but that, with communication, “we could start maybe mid September, and it could take a couple weeks to get it completed” (Presenter - Road Department (Speaker 6)). County staff also discussed gravel gradation and whether crushed material could be obtained locally or would need to be stockpiled to meet PI specifications.
On a motion to accept Williams Excavation’s bid for $740,454.26 and to authorize county officials to sign the construction contract (moved by Speaker 1; second recorded), the commission voted in favor and the motion carried. County staff noted some details remained to be finalized — notably the gravel source and specification — and that staff would bring final contract documents for signatures once those items are clarified.
Why it matters: the project is intended to stabilize and gravel a segment of Cattail Bay Road the county says needs structural improvements. Road staff indicated partial reimbursement from the state is expected for about $300,000, and the work is timed to avoid peak harvest impacts if possible. The commission directed staff to proceed with contract execution once technical specifications are confirmed.
The commission did not record a roll-call tally in the minutes; staff said the motion carried and the county will return with the fully executed contract and any final clarifications on gravel sources and the project schedule.