Cushing selectmen accept winter-materials bids, confirm Lane Construction paving deadline with penalties
Summary
The Selectmen awarded the salt contract to New England Salt Co., LLC at $64.95/ton and the sand contract to Heartland at $11.00/cy, and noted Lane Construction must finish paving by July 30, 2015 or incur a $100-per-day penalty; a resident asked whether the contract includes an inspection clause.
Get email alerts on the Procurement Paving topic
No spam. Unsubscribe anytime.
At the May 26 meeting, the Cushing Selectmen accepted bids for winter road materials and confirmed the town’s paving contractor and schedule.
Chairman Alton Grover read salt bids and the board accepted the low salt bid from New England Salt Co., LLC at $64.95 per ton. The board also accepted Heartland’s sand bid at $11.00 per cubic yard, which the bidder stated includes use of a dozer. Both procurement motions passed unanimously (5-0-0).
On road work, Chairman Alton Grover reported that Lane Construction has signed the paving contract and is scheduled to complete the work by July 30, 2015; the contract includes a liquidated-damages provision of $100 per day for missed completion. Grover asked Lane Construction to inspect a bump on Spear Mill Road and report back.
Resident Daniel Remian asked whether the paving contract includes an inspection clause; Chairman Grover replied the contract does not include an inspection clause but that he spoke with John Wood from the State about prior projects and said the contractor will use binder, not a sand mix, in Cushing.
Votes at a glance: salt contract awarded to New England Salt Co., LLC ($64.95/ton) and sand contract to Heartland ($11.00/cy); both votes carried 5-0-0. The board did not adopt an inspection clause at this meeting and the pavement-completion deadline and penalty were reported as contract terms.