Scituate commission closes hearing for 83 Rebecca Road after applicant pulls house back from seawall and increases mitigation
Summary
The Commission closed and will issue an order for a raise‑and‑reconstruct project at 83 Rebecca Road after the applicant reduced footprint, moved the house farther from the seawall and increased mitigation plantings; the commission required standard coastal conditions such as open understructure and a protective post‑and‑rope fence.
Get email alerts on the Raise And Reconstruct topic
No spam. Unsubscribe anytime.
The Scituate Conservation Commission voted to close the hearing and issue orders for a raise‑and‑reconstruct project at 83 Rebecca Road after the applicant revised plans to move the primary dwelling farther from the seawall, reduce building footprint and increase mitigation plantings.
Dylan Brady (Grady Consultants) said the revised plan increased the mitigation planting area from about 115 sq ft to 207 sq ft, reduced the impervious increase to roughly 20% and pulled the new footprint slightly farther inland. Coastal geologist Stan Humphreys provided a supplemental letter concluding that the revised elevation and design meet the local performance standards for land subject to coastal storm flowage and that setting the lowest horizontal structural member at 3.6 ft provides resiliency against sea‑level change over the structure’s life.
Commissioners asked that the house remain open underneath (no enclosures or lattice), that driven timber piles be used rather than footings, and that a simple post‑and‑rope protective fence be installed to preserve mitigation plantings and dune vegetation. The applicant agreed to those standard conditions. Commissioner Penny moved to close the hearing; the motion passed and the Commission will issue the order of conditions with the stated protections.
Next steps: the Commission will draft an order of conditions including required protective measures (open understructure, no lattice/enclosure, driven piles, post‑and‑rope protective fence and specified mitigation planting details).