Staff recommends $1.52 million Blunt Construction contract for Shoal Creek Road reclamation
Summary
Public Works Director Robert Drew told commissioners the county received competitive bids for full depth reclamation on Shoal Creek Road and recommended awarding a $1,524,616.45 contract to Blunt Construction, with a 10% contingency and a Georgia DOT grant of $497,689 contributing to the project.
Get email alerts on the Roads And Infrastructure topic
No spam. Unsubscribe anytime.
Public Works Director Robert Drew presented the results of bids for IFB 467‑25, a full depth reclamation (FDR) project on Shoal Creek Road from the historic courthouse to State Route 136 (excluding the bridge and roundabout areas).
Drew said Blunt Construction was the apparent low bidder and staff recommends awarding a contract in the amount of $1,524,616.45 and adding a 10% county contingency to cover potential minor changes and unforeseen issues.
He told the board the county received a Georgia Department of Transportation grant of $497,689 toward the project and that the city of Dawsonville will pay a portion under an intergovernmental agreement (IGA). Drew said the low bids came in favorably compared with an earlier estimate and that procurement followed the county's legal advertising requirements.
Commissioners discussed timing with the bridge closure and an upcoming roundabout construction, including contractor access and hauling logistics. Drew said staff expected to sequence work so the contractor could complete FDR before the bridge opens and that weather will also affect schedule.
Next steps: staff requested authority to accept bids and prepare an award recommendation to the board for a future voting session; no formal contract award was recorded during the work session.