Township road project hold‑up: asphalt test showed excess voids; contractor appeal may affect $13,000 payment
Summary
A DOT test found Compromise Road asphalt exceeded allowed voids; the contractor was told to refund part of the cost, has appealed, and if the appeal fails the township expects a $13,000 refund and grant closeout is delayed.
Get email alerts on the Infrastructure topic
No spam. Unsubscribe anytime.
Mayor Asay told the committee the township has not received final payment for the Compromise Road project because a test of the asphalt showed more voids than allowed. Fralinger Engineering's Mulford reported the result to the committee.
As a result, the New Jersey Department of Transportation directed the contractor to refund a portion of the cost to the municipality; the contractor has filed an appeal with DOT. If the contractor's appeal is unsuccessful, the township expects a refund of $13,000. The lack of a final closeout is holding up the remaining grant money from the State.
The committee did not take additional action at the April 4 meeting; members recorded the status and next steps are contingent on DOT's appeal outcome.