Northfield advances Phase 1A of new police station; contract to appear on next agenda

Village of Northfield Village Council · October 28, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Law Director Brad Bryan and Engineer Dan Collins said the village is preparing a builder contract for Phase 1A of a new police station with a not-to-exceed estimate near $1.3 million; the Summit County Building Department gave conditional approval to Phase 1A plans and the village must consolidate two Village Hall parcels before occupancy.

Mayor Jenn Domzalski opened the Oct. 9 Village of Northfield council meeting with updates on the police station and municipal complex. Law Director Brad Bryan said he and Engineer Daniel Collins are finalizing a contract with the builder for Phase 1A of the new police station and expect the measure to be placed on the next council agenda; Bryan said the contract will carry a "not to exceed" cost in the vicinity of $1.3 million.

Engineer Daniel Collins told the council the Summit County Building Department sent conditional approval late that afternoon for the Phase 1A plans for the new police station. Collins also reported the Cambridge Road Project is about 98% complete and that he is preparing punch-list items to present to the contractor.

Collins said the village will need to consolidate two Village Hall parcels in connection with the future municipal complex projects and is seeking quotes from surveyors; he added that consolidation must occur before the new building receives an occupancy permit at the conclusion of construction. Mayor Domzalski and councilmembers did not take a formal vote on the contract at the Oct. 9 meeting; Bryan said the formal contract will be introduced at the next meeting.

Votes at a glance: Council approved the Sept. 25, 2024 minutes on a motion by Councilmember Renell Noack, seconded by Alan Hipps. Roll-call: Jesse Ferko-abstain; Noack-yes; Gary Vojtush-yes; Nicholas Magistrelli-yes; Alan Hipps-yes; Kevin Lewis-yes. The meeting adjourned on a motion by Hipps, seconded by Kevin Lewis; Noack, Vojtush, Magistrelli, Hipps and Lewis voted yes and the meeting ended at 7:44 p.m.

Next steps: the Phase 1A contract language and the not-to-exceed figure will appear on the next council agenda for formal consideration; surveyor quotes for parcel consolidation are being solicited.