Zoning officer reports Miller Farm and Blackhawk subdivision progress
Summary
Zoning Officer Matt Shock reported on Blackhawk Phase-D detention-basin acceptance pending HOA punchlist, and progress across Miller Farm Sections 1–3A including pump station work and permit inquiries for 32 homes.
Get email alerts on the Zoning Development topic
No spam. Unsubscribe anytime.
Zoning Officer Matt Shock told council that the Blackhawk Phase-D inspection and maintenance agreement for the detention basin has been signed by the homeowners association; village engineering consultant KEM will verify remaining punch-list items before final subdivision acceptance.
Shock said Miller Farm Section 1 public infrastructure is complete except for the pump station, which is under construction, and that inquiries for individual building permits for 32 homes have begun. Miller Farm Section 2 improvement plans for phases A, B and C have been approved and construction is underway; Section 3A has its first submittal package received. Planning and Zoning had no comments on a submission and KEM comments were relayed to EMH&T.