Council approves $7,918 grit pump purchase for wastewater plant after equipment failure
Summary
City staff reported a recent failure in the wastewater treatment plant grit pump and the council authorized a sole‑source purchase from Haines Equipment for $7,918 to expedite replacement and avoid further system damage.
Get email alerts on the Wastewater Infrastructure topic
No spam. Unsubscribe anytime.
The Tonganoxie City Council on July 6 authorized a $7,918 purchase to replace a failed grit pump at the city's wastewater treatment plant.
Mister Porter explained that a grit pump removes abrasive materials (sand, gravel, silt) that otherwise damage downstream equipment in the treatment process. Staff solicited bids; the city received an incomplete response from other vendors and identified a compatible unit from Haines Equipment. Because the quoted unit is compatible with the existing plant equipment and the failure required fast replacement, staff recommended approving the purchase under a sole-source justification to expedite repairs.
Council member Mister Dale moved to authorize the purchase from Haines Equipment for an amount not to exceed $7,918; the motion was seconded and carried on a voice vote. Porter said the cost will be charged to the sewer operations fund and staff will monitor the fund through year-end.
Next steps: Staff will expedite ordering and installation and use city sewer-plant staff to install the unit.