Sherman committee approves Newfield $5.01 million progress payment, multiple invoices and contingency releases

Town of Sherman School Building Committee · May 18, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The School Building Committee approved a series of vendor invoices — including a $5,009,652.21 progress payment to Newfield — and authorized contingency releases totaling up to $415,891.00. The committee also approved insurance, testing and architect invoices and a $1,000 amendment for material testing in the D-Wing.

The Town of Sherman School Building Committee on May 18 approved a set of vendor invoices and two contingency releases tied to the ongoing school renovation.

Chair Kerry Merkel moved and the committee unanimously approved two progress-payment invoices to Newfield Construction dated March 31 and April 30 totaling $5,009,652.21. The vote followed consideration of multiple other invoices tied to the project.

The committee approved the Construction Solutions Group (CSG) invoices (3/6/26 and 4/10/26) for $4,340.28 (Sherman School portion), Antinozzi Associates invoices (3/31/26 and 4/30/26) for $60,259.13 (Sherman School portion), Meyer move-management storage invoices for $1,682.96 (Sherman portion), and Special Testing Laboratories invoices totaling $19,180.23 (Sherman portion). The committee also approved a CIRMA builder’s risk insurance invoice dated Dec. 23, 2025 for $115,071.16 for the Sherman School portion.

Kerry Merkel moved to approve Amendment #15 — a $1,000 authorization for Pennoni to perform testing and sampling of material found in the D‑Wing; the committee recorded the testing as non-hazardous and approved the work.

Finance and contingency actions were handled after a review of the change-log. Tim Laughlin reported that, from a billing perspective, the project was about 30% complete at the end of April with projected billing of 40% at the end of May and 50% at the end of June. He said combined contingency reserves were approximately $1.7 million if the change orders reviewed were approved. Laughlin moved to authorize up to $120,471.00 from the construction management contingency for listed PCOs on the Sherman Open PCO Log dated May 13, 2026, and moved to authorize up to $295,420.00 from the owner’s management contingency for owner-listed items on the same log; both motions were seconded and approved.

All votes were recorded in the minutes as "All in favor." No recorded objections or roll-call vote tallies were included in the meeting record.

The committee did not take public comment and set its next regular meeting for Monday, June 15, 2026.