Village Park Phase II work nears completion; PARC schedules Movie in the Park for June 20
Summary
Council received an update that fencing and court resurfacing for Village Park Phase II are complete and plantings were installed; the council will decide whether to epoxy-coat the amphitheater and add disc-golf plantings. The PARC Committee will host Movie in the Park (Moana 2) on June 20, 2025.
Get email alerts on the Parks topic
No spam. Unsubscribe anytime.
Administrator Dan Corder told the council that Village Park Phase II has completed fencing and resurfacing work for the tennis/basketball courts and installed green-giant plantings along the new property line. Remaining items include a council decision about epoxy-coating the amphitheater concrete and whether to add additional plantings in the disc-golf area.
Council Member Mark Baker reported that the PARC Committee will host the first Movie in the Park of the year on June 20, 2025 at 8:30 p.m.; the film will be Moana 2 and refreshments will be provided by the PARC Committee.
No formal motions were recorded to change project scope or funding during the update; the minutes reference attachments for the park project progress. Any decision to epoxy-coat concrete or add plantings would be a further action requiring direction or a motion at a future meeting.