Athens board approves $147,969.62 pay request, multiple change orders and engineering amendment for WWTP project
Summary
At its Jan. 26 meeting the Athens Village Board approved Pay Request #6 of $147,969.62 to contractor August Winter, approved several change orders and an $18,500 engineering amendment for the wastewater treatment plant project, and accepted a $30,100 bid for a Sodimate enclosure.
Get email alerts on the Wwtp Project topic
No spam. Unsubscribe anytime.
The Athens Village Board on Jan. 26 approved a series of actions related to the village wastewater treatment plant (WWTP) project, including a $147,969.62 pay request to contractor August Winter, multiple change‑order approvals and an engineering amendment.
Trustee Perkins, reporting for the Water & Sewer Committee, said the committee had considered several change‑order requests and recommended board action. The board approved August Winter’s Change Order Requests #1, #3, #4, #5A and #7 and denied Change Order Request #6. The board also approved Pay Request #6 from August Winter for $147,969.62.
The board approved MSA’s engineering amendment #1 for the WWTP project in the amount of $18,500. The board accepted SD Ellenbecker’s proposal to furnish a Sodimate enclosure for $30,100.
All WWTP motions were taken following the Water & Sewer Committee report and carried by the board; no roll‑call vote tallies were provided in the meeting record for these motions. Trustee Perkins was the member who presented the committee recommendations to the board.
The approvals move forward contractor payments and specific contract changes tied to the WWTP work; the board did not record further technical details about the approved change orders in the meeting minutes. The meeting adjourned at 7:33 p.m.