Lyndon Station trustees approve WWTP pay apps and one change order pending agency sign-off

Village of Lyndon Station Board of Trustees · March 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Trustees approved Draw Requests Pay App #9 and #10 and approved Change Order Request #2 for the village wastewater treatment plant project, each contingent on RD approval; Change Order Request #3 was tabled for later consideration.

Trustee Morgan Place and Trustee Rebecca Coley led action on wastewater-treatment-plant spending at the March 9 Village of Lyndon Station board meeting. The board voted unanimously to approve Draw Request Pay App #9 and Pay App #10 for bills related to the WWTP project, each contingent on approval from RD.

Trustees also approved Change Order Request #2 for the WWTP project, again contingent on RD approval. Trustee Coley moved to table Change Order Request #3; Trustee Place seconded and the motion to table carried unanimously. No public debate or votes opposing the actions were recorded in the minutes.

The board indicated it is relying on the RD review before funds or contract modifications proceed. The board did not provide additional details in the minutes about the dollar amounts in the pay apps or the specific scope changes in the change orders; that information was recorded as contingent on RD and was not specified in the meeting record.

The board will revisit the tabled change order once additional information is available or after RD provides its determinations.