Committee hears progress updates on middle-school roof, gym work and other projects
Summary
The Coventry school building committee was told a $4.324 million middle-school roof contract has been awarded and is moving toward execution, gym and auditorium work is scheduled, RFIs and pay applications are under review, and several smaller projects (paving, asbestos tile removal) remain on track.
Get email alerts on the Construction Projects topic
No spam. Unsubscribe anytime.
The Coventry School Building Committee received progress updates on multiple construction projects, including a fully executed notice to proceed for a middle-school roof replacement and near-term work on the gym and auditorium.
Presenter reported that Greenwood Industries was awarded the partial roof replacement contract for Alan Shawn Feinstein Middle School with a total contract value of $4,324,000 and that the notice to proceed has been executed, allowing the contractor to begin submittals and early procurement. "Total contract value of 4,324,000," the presenter stated. Two submittals have been filed so far; staff said a schedule and any remaining procurement timeline should be available after the contractor completes final execution, with a target follow-up by July 10.
Committee members discussed sequencing the work to avoid classroom disruption. Staff said a goal remains to have contractors out of core classroom areas by the start of school while permitting work in other roof areas that can be scheduled around school operations. The group flagged foam insulation as a potential long-lead item and noted rain, extreme heat and unforeseen demolition (for example, water-damaged structural members) as possible causes for schedule or cost impacts.
On smaller projects, the OPM update covered recent pay applications and RFIs: Jensen Hughes provided responses to contractor RFIs and staff reported a roughly $9,000 credit tied to town permits on the job-cost summary and a change in the builder's-risk line item (builder's-risk figure referenced in discussion). Gym work was reported to run from the 7th through the 17th, with the auditorium and kitchen to follow. Committee members suggested targeted additions such as protective covers for sprinkler heads and sensitive equipment using modest savings; staff said the contractor will be asked for proposals if the committee directs it.
Separately, asbestos 9-by-9 tile removal in older school areas is underway with tiling and remediation planned next, and Hopkins Hill paving is expected late this month using impact-fee funds after the committee accepted the low bid.
The meeting closed with routine scheduling discussion; staff will circulate any updated contractor schedules and follow up by email if status changes.
Next steps: staff to circulate the roof contractor's full schedule when received, request cost proposals for any proposed small-scope safety covers, and continue to monitor RFIs and pay applications.