DeSoto County approves change order and trailhead buildings for Johnson Creek Greenway
Summary
The Board approved a $13,164.65 change order to Johnson Creek Greenway Phase 2, authorized pavilion construction with Murphy & Sons for $69,378 and a Tomco labor contract for restroom construction for $31,250; the county will supply restroom materials.
Get email alerts on the Parks Greenways topic
No spam. Unsubscribe anytime.
DeSoto County supervisors approved multiple updates to the Johnson Creek Greenway on May 18, including a change order for Phase 2 and contracts for trailhead facilities.
Supervisor Ray Denison moved to accept a change order that adds 15 days to the Johnson Creek Greenway Phase 2 schedule and increases contract cost by $13,164.65 to allow ordering and setting additional piers; the motion passed by recorded vote.
Road Manager Robert Jarman presented three quotes for a pavilion at the Johnson Creek trailhead and recommended Murphy and Sons, Inc. at $69,378 to provide building and construction. For the restroom facility the board approved Tomco for labor only at $31,250 with the county providing materials. The motion approving both contracts passed by recorded vote.
Why it matters: The change order addresses a construction sequencing need that adds both time and cost; the pavilion and restroom contracts fund amenities intended to improve user experience on the trail.
Board direction and timing: The board authorized the Board President to sign the change order and contracts. The minutes do not contain a construction schedule beyond the added 15 days noted in the change order.