Council signs water draw packet; contractor punch‑list, CDBG funding and Neptune meter update discussed

Town of Twin Bridges Regular Council · August 12, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved and signed a draw packet for the ongoing water project after Great West reported substantial underground work is complete and contractors have until the end of August to finish punch-list items or face penalties; new Neptune water meters have arrived for installation.

The Twin Bridges Town Council approved and signed a draw packet for the town’s water project on Aug. 12 after receiving an update from Great West and project staff.

Town staff reported substantial underground work is complete, and contractors must finish cleanup and outstanding punch-list items by the end of August or face penalties; the town’s bond could cover repairs if contractors fail to complete the work. Council also noted that current-year CDBG funds remain available and have not been used for the water-tank project; staff requested confirmation to pursue those funds and asked community members for letters of support.

Councilor Nolan Frandsen moved to approve and sign the draw packet; Councilor Jordan High seconded and the motion carried unanimously. The minutes record that Great West’s well project is in final review before submission to DEQ. Separately, new Neptune meters have arrived and will be installed; the remaining meters are on order.

The draw-packet approval authorizes the town to proceed with draw requests tied to project milestones; the minutes do not list dollar amounts or contract-signing dates, and staff said Craig and Austin will send the town a contract.