Hillsborough engineers present water asset-management plan, note lead-service line work and funding deadlines

Town of Hillsborough Water & Sewer Commission · December 5, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Underwood Engineers presented a draft water asset-management plan to the Hillsborough Water & Sewer Commission, outlining inventory, condition assessments and prioritization scoring and flagging estimated costs for lead-service-line identification and replacement under the EPA—s revised Lead and Copper Rule; NHDES and town staff confirmed training and disbursement dates.

Margaret Blank of Underwood Engineers presented the Town of Hillsborough—s draft water asset-management plan at the commission—s Dec. 5 meeting, describing the system inventory, condition assessments and a scoring method used to prioritize maintenance and replacements. The presentation included a financial overview and an estimated replacement-cost projection that incorporated the anticipated expense of identifying and replacing service lines to comply with the EPA Lead and Copper Rule Revision (the minutes do not specify a dollar figure).

Commissioner Dave Lewis asked that the map key for water assets be consistent with the sewer asset management plan previously prepared by Underwood Engineers; Blank said she would review the maps to ensure the keys match. Blank said she expected to deliver copies of the complete draft report to the Commission on Friday, Dec. 6.

Kaitlyn Curtis of the New Hampshire Department of Environmental Services (NHDES) emphasized the importance of keeping ArcGIS and the asset-management plan current, calling the tools invaluable for planning and long-term maintenance. Blank noted the final ArcGIS training is scheduled with Administrator Penny Griffin and Cody Boisvert for Dec. 19. Blank also said the final disbursement request to NHDES was due Dec. 31, 2024; Curtis confirmed NHDES would accept the final disbursement request through Jan. 31, 2025.

The presentation framed the asset-management plan as a foundation for planning and budgeting but did not include final cost figures; commissioners requested map-key consistency and the firm indicated it would provide a completed draft for review the following day.