Citizen Portal
Sign In

Get Full Government Meeting Transcripts, Videos, & Alerts Forever!

Get email alerts on the Wastewater Infrastructure topic

No spam. Unsubscribe anytime.

Two new Inovair blowers set in Hillsborough wastewater plant; final swap scheduled for early December

Town of Hillsborough Water & Sewer Commission · November 13, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Two new Inovair blowers are now in place at the wastewater facility; fabrication of intakes and exhaust manifolds will be done on site and the final original blower is tentatively scheduled to be turned off Dec. 2 to allow installation of the last new unit.

Commissioner Dave Lewis updated the Commission Nov. 13 on the Wastewater Facility Blower Replacement Project, reporting that two new Inovair blowers are set in place at the plant. Fabrication of the air intakes and exhaust manifolds will occur on site because of logistical concerns raised by contractor R.H. White.

Tentatively on Dec. 2 the remaining original blower will be shut down so the final new blower can be installed, and an Inovair representative is expected on site Dec. 10 to assist with final commissioning steps.

Why it matters: the blower replacement is a capital maintenance project required for proper operation of wastewater treatment processes; the installation schedule affects plant operations and contractor logistics.