Tioga commission approves $2.2 million in contractor payments, accepts trail change order

City Commission of the City of Tioga · September 16, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The commission voted to accept Change Order #1 for the Tioga Dam Nature & Recreation Trail, approved a $1,285,456.03 pay application for North Main Street Reconstruction and approved a $786,251.70 pay application to FCI Constructors for the community center; Knife River patching proposal for $167,100 was also approved.

City commissioners on Sept. 16 approved multiple large contractor payments and a change order covering ongoing public works projects.

Engineer Josh Reiner reported on several capital projects and presented Change Order #1 for the Tioga Dam Nature & Recreation Trail Phase 1, proposing the use of landfill millings rather than gravel for the trail base; the commission discussed the engineering recommendation and voted to accept Change Order #1.

The commission approved Contractor's Application for Payment #3 for the North Main Street Reconstruction in the amount of $1,285,456.03. Commissioners also approved FCI Constructors' Application for Payment #2 for work on the Tioga Community Center in the amount of $786,251.70; FCI reported the bulk of the payment covered earthwork and utility work. Separately, the commission approved a Knife River proposal for asphalt patching priced at $167,100.00.

Reiner also updated the commission on the Water Service Line Inventory required under the Lead and Copper Rule, noting the city must conduct a customer survey, develop a sample site plan and send notifications to water customers.

These votes moved multiple capital projects forward; commissioners indicated forthcoming walk-throughs and scheduling for striping and seeding on completed roadwork. The commission approved each pay application and the Knife River proposal by roll call.