Hillsborough commissioners request easement, 8‑inch mains for proposed Avanru subdivision; note missing as‑builts

Town of Hillsborough Water & Sewer Commission · February 12, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Commission sent Planning Board comments requesting a 40‑ft temporary/20‑ft permanent easement for a future water main and that all project mains be 8‑inch ductile iron; commissioners also noted Avanru has not provided as‑built plans for 219 West Main Street.

The Town of Hillsborough Water & Sewer Commissioners reviewed a Planning Board application note on Feb. 12 for the proposed Avanru development (Map 11O Lot 152) and submitted technical comments to the Planning Board. The Commission requested that the developer add a 40‑foot temporary construction easement and a 20‑foot permanent easement to the plan to permit future installation of a water main, and that all water mains installed as part of the project be 8‑inch ductile iron.

Commissioners noted that no complete application had been received yet; they said a full technical review will follow upon receipt of a complete application. The Commission also said it will provide the Planning Board with the water‑looping study and a map to illustrate why the easement and main sizing are necessary for future system connectivity. Separately, the minutes record that Avanru has not supplied the requested as‑built plans for the 219 West Main Street water and sewer main installation despite prior requests.

The comments are advisory to the Planning Board and are intended to ensure future compliance with the town’s water design and construction standards. The minutes do not record a formal vote on these comments.