Paving project complete but punch‑list remains; council hears engineering report

City of Bottineau Council · November 4, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Wold Engineering told the Bottineau council the 2024 paving is finished but driveways, sidewalks and dirt work remain; striping is scheduled, Mayo Construction faces liquidated damages, and a manhole needs its height lowered.

Wold Engineering representatives Jessica Tagastad and Jesse Brandvold reported to the Bottineau City Council on the status of the 2024 paving project.

According to the minutes, paving work itself is finished. Remaining items include some driveways, sidewalk repairs and dirt work. Mayo Construction is scheduled to apply striping to the streets this week. The city is assessing liquidated damages against Mayo Construction for failing to complete the project on schedule. Engineers also noted a manhole that requires its height to be lowered.

City crews have reinstalled mailboxes that had been removed for construction and repaired a couple of damaged fences, the minutes say. No change orders or additional costs tied to these repairs were recorded in the meeting record.