Wold Engineering reports street work progress; resident warns paving has damaged boulevard trees
Summary
Wold Engineering told the council that concrete work is nearly finished on 2nd St. E. and Kersten Street base stabilization is about to begin. Resident Kenny Fix said paving damaged many boulevard tree roots on Kersten; Council President Seykora will consult Wold and Shade Tree representatives to try to preserve trees.
Get email alerts on the Streets And Trees topic
No spam. Unsubscribe anytime.
Jessica Tagastad and Jesse Brandvold of Wold Engineering updated the council on local infrastructure projects, saying the 2024 Street Project is progressing well. Tagastad reported that concrete work is nearly finished on 2nd St. E. and that Kersten Street has been cleared and base stabilization will begin before concrete crews return.
Resident Kenny Fix told the council that the street paving work on Kersten Street damaged the roots of several boulevard trees and expressed concern that the trees — many of them ash — may be removed or die. Council President Seykora said she would coordinate with Wold Engineering and Shade Tree representatives to explore measures to preserve as many trees as possible.
Wold Engineering also reported that the city received the final bill from Kemper Construction for the 2023 Water Line Project. No contract disputes were reported at the meeting. The council did not take formal action on tree mitigation at the Aug. 5 meeting and asked staff and engineers to follow up before the next meeting.