Town praises quick repairs after monthlong Hydro Tech maintenance contract

Swepsonville Town Council · April 30, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Town staff reported early results from a proactive Hydro Tech maintenance contract for pump stations, saying crews cleared debris, repaired a broken pump shaft on-site, rewired a high-level alarm, and addressed blockages, and staff said the on-site repairs are already beginning to offset monthly contract costs.

Brad (S2) told the Swepsonville council the town is a little over a month into a proactive maintenance partnership with Hydro Tech at its pump stations.

"Each week, they allot 4 hours," Brad said, explaining Hydro Tech divides that time among stations and has been able to clean debris, jet lines, and perform on-site repairs including replacing a broken shaft and rewiring a high-level flow alarm channel. Brad said those on-site repairs and preventative work have begun to recoup the monthly investment.

Brad also said crews found and removed blockages caused by a broken-off PVC piece and improved alarm communication to give staff earlier notice of high flows. Council members asked for details about longer-term performance and potential cost savings; Brad said staff are pleased with the contractor's responsiveness so far.

Why it matters: brief, targeted preventative maintenance and the ability to perform some motor repairs on-site can reduce downtime and larger emergency costs for municipal wastewater infrastructure.

Next steps: staff will continue to monitor Hydro Tech performance and report outcomes to the council, with an expectation to assess cost-effectiveness after several months.