Summary

Staff and engineering raised concerns about an off‑site grading easement that affects city park property on Bison Trail and steep grades at Lot 66; engineering said the easement must be cleared with City Council before final plat recording and recommended benched slopes rather than 3:1 where feasible.

The commission examined a preliminary plat for the Crossings at Hidden Creek Phase 1, a development that would create 99 single‑family lots. Staff and engineering highlighted two principal issues: grading that encroaches on city park property to the northeast (Bison Trail) and steep grades on Lot 66 that could raise drainage or constructability problems.

Staff said the developer shows an off‑site grading easement over city property and expressed concern about stormwater and steeper grades than previously approved in the ECP. City engineering said the off‑site grading should be benched rather than a straight 3:1 slope to reduce runoff impacts and that the grading easement must be approved by City Council prior to recording the final plat.

The applicant’s representative, Landon Lisonbee, said the work matches an approved ECP and expected to coordinate with engineering; Brian Rauschner (engineering) recounted prior internal work to determine how the city would procure or approve the easement and said council approval would be tied to final plat recording.

Next steps: Engineering will continue coordination with the developer; the off‑site grading easement will be a condition for final plat approval and must be resolved with council before recording.