Council approves repairs, paving contracts and $75,907 museum roof replacement from hospitality fund

Greenwood County Council · June 17, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council authorized contract negotiations to repair Gate 2 at the Buzzard's Roost hydroelectric facility, awarded the 24/25 paving contract to Satterfield Construction, approved a federal grant application for an airport access road with a $16,000–$20,000 local match, and approved a $75,907 hospitality-fund payment and procurement variance to replace the county museum roof.

County Engineer Rhett Templeton told the council damage to Gate 2 at the Buzzard's Roost hydroelectric facility occurred during Hurricane Helene. Staff bid the repair work under procurement policy and said the low bidder (named in the record as 'Chienbro' / 'Chienbro') was acceptable to the county's insurance reviewer; council authorized negotiations to proceed with that bidder.

Templeton also recommended awarding the 24/25 local paving contract to Satterfield Construction as the low bidder; council approved the award unanimously. The county will use CTC funds for paving and staff noted the 24/25 funding cycle timing.

On airport access, Templeton explained a phased project for an access road at Greenwood County Airport that is largely eligible for federal funding; the county's local match is estimated between $16,000 and $20,000 depending on final details. Council approved proceeding with the grant application and contractor selection.

Facilities staff described long-running water intrusion and interior damage at the county-owned museum. United Contracting and Roofing submitted the lowest quote at $75,907 to replace the tar-and-gravel roof with a TPO (thermoplastic) roof. Because that low bid exceeded the local vendor by more than 5%, staff requested a procurement variance and council approved a resolution to use $75,907 from the hospitality tax fund balance and grant the variance to move the project forward immediately.

Why it matters: repairs at the hydroelectric facility, paving and airport improvements affect infrastructure resilience and mobility; the museum roof repair addresses ongoing building damage and interior hazards, and uses hospitality-tax fund balance for an urgent capital repair.

Attribution: contract and project details were provided by County Engineer Rhett Templeton and Deputy County Manager Stephanie Dorn; procurement details and bid amounts are recorded in the meeting transcript.