Sturgis approves $10.8 million contract for natural-gas generator project

Sturgis City Commission · July 9, 2026
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Sturgis City Commission approved an engineering, procurement and construction agreement for a natural-gas generator project and a 5% contingency, moving forward a plan for three reciprocating engines to add 7.5 MW of local generation capacity.

The Sturgis City Commission on July 14 approved an engineering, procurement and construction contract for a natural-gas–fueled generation project and a separate contingency budget to move the project into procurement.

City staff said the project, included in the fiscal year 2027 capital budget, will add three reciprocating engines with a combined output of about 7.5 megawatts and will use natural gas as fuel. City presenter Chris said staff selected the Fawn River substation site because of its proximity to a high-pressure gas line and that the project has a renewed operating rating permit from EGLE. "This contract is required to move forward for procurement of the engines and equipment needed to complete the project," Chris said.

At the meeting a commissioner moved to approve the agreement with McCallis and Cat in the amount of $10,785,000; the motion passed by voice vote. The commission also approved a 5% contingency of $539,250, which staff said will cover procurement contingencies.

Staff told commissioners the Michigan Public Power Agency helped model the project’s value to the city through capacity offsets and potential transmission-cost savings; additional agreements to be brought back include operation and maintenance, a long-term service agreement and a monitoring/dispatch agreement.

The vote authorizes staff to proceed with ordering equipment and advancing the procurement process. Commission discussion focused on project scope, permitting and future agreements; no member registered an objection during the recorded voice votes.

Next steps listed by staff include finalizing the procurement paperwork and returning to the commission with O&M and service agreements prior to entering long-term commitments.