Council hears update on Crouse Park work; town funds and contracts detailed

Allegheny County Council · August 12, 2024
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Staff reported Allison Construction has begun phase 1 of the Crouse Park project; phase 1 is $18,350 and phase 2 is $15,800, with total project funding collected about $45,000 including a $10,000 town contribution.

The council heard a project update on Crouse Park improvements at its July 16 meeting.

A staff member (S11) said Allison Construction has started phase 1, which covers fencing and site preparation. "That portion of the contract is $18,350," the presenter said, adding that phase 2 (finishing the court and related site work) is $15,800. Earlier estimates showed combined costs of about $31,700, but staff now estimate roughly $34,000 is needed to complete phase 2 and final work.

The presenter said the town committed $10,000 to the project and that the remainder of funds came from countywide contributions and grant sources; total funds collected for the project are approximately $45,000. Staff indicated they expect to receive the signed contract back this week and to process the phase 1 payment when work is complete.

Council members asked about landscaping plans; staff said schematics for landscaping and funding sources will be presented next month.

No formal vote was taken on the project at the meeting; staff will return with the signed contract and a payment request.