Summary

Town manager presented an engineer'level estimate of about $427,000 for a six-inch Sparta Parkway water line and outlined financing under a state statute that would let a private contractor build to municipal specs, with attorney and total construction costs still to be determined.

The Sparta town manager told council an engineering proposal for replacing or extending a six-inch water line on Sparta Parkway carries an estimated price tag of about $427,000, not including contractor bid/labor costs. "I'll just go ahead and tell you the number of $427,000 for a 6 inch line," the manager said, noting the figure covers engineering, permitting, design, a 10% contingency and construction observation.

The manager presented an option under North Carolina General Statute 160A-499 that would let a private contractor construct infrastructure to municipal specifications and be reimbursed over time, potentially speeding construction without the town advancing the entire capital budget up front. "They utilize North Carolina General statute 160A-499... to reimburse a private contractor for that infrastructure if that infrastructure is built to the specs established by the municipality," the manager said.

Council members pressed for clarity on total costs beyond the engineer's estimate, including likely attorney fees and construction labor. The manager said the engineering/administration portion alone was estimated in the transcript at roughly $64,000 (planning, permitting and construction observation) and that attorney fees for structuring a contractual reimbursement approach were unknown. "We do not know the total cost of what [attorney fees] would be," the manager said; he committed to request a firm estimate from the law firm advising on prior projects.

Council discussed alternatives including traditional municipal borrowing and direct town-led construction; some members noted long-term reimbursement or sales-tax capture models could stretch the payback timeline. The manager said if the town engaged the private option, the contractor would build to municipal standards and the town would take ownership of the completed infrastructure, paying only for the cost of construction through the agreed reimbursement mechanism.

No vote was taken on the project at the meeting. The manager said the item would return for further discussion and that staff would provide the engineering report and attorney cost estimates at a future meeting before any formal decision.

The council also discussed required permitting and inspections (DEQ inspection and engineer sign-off) and asked staff to supply the full engineer'level itemization before any formal procurement or financing decision.

Next steps: manager will provide the full engineer's report, request an estimate of attorney fees from the advising law firm, and place the item on a future council agenda for possible action.